National mobility concept · pre-feasibility

Build evidence
before lines

The revised 2052 concept separates railway infrastructure, passenger services and access objectives. Existing and restorable rail comes first; new mountain rail is no longer assumed simply because a region needs better transport.

Independent pre-feasibility concept. This is not an approved Government of Armenia programme, an operator commitment or an international agreement.

Key change. The earlier R1–R7 full-build idea is retired. The public concept now has four core rail corridors, official regional interfaces and conditional access studies.

2027–2052 horizonConstant 2026 USDEnglish + ArmenianUpdated 9 Sep 2026
4core rail corridors: R1–R4
3 viewsstatus, passenger services and terrain are separated
Gate SSouth Armenia becomes a multimodal access decision
No fixed totalthe programme is repriced only after scope is fixed

Evidence and arithmetic audit

Clear about certainty

Facts separated

Observed data, planning targets, assumptions and decision gates use different labels

Totals reconciled

Earlier $18.95–29.30bn sum is archived; the revised programme needs fresh pricing

Alternatives retained

Gate S compares regional reopening, coach, feeder and road investment; no new domestic mountain rail is a valid outcome

Unknowns left open

Annual demand, revenue, subsidy, fleet and power are not invented before modelling

Direct trains ≠ direct tracks

A passenger should not have to change trains simply because the infrastructure corridor ID changes. Where capacity, rolling stock and operating rules allow, one train can continue across several corridors. A buildable railway still has to compete on door-to-door time and whole-life cost.

Infrastructure

Where tracks can realistically exist

Service

Where one train can continue

Time

Whether the journey is competitive

Gate

Whether construction is justified

Map system

Two questions,
three views

The two network maps are interactive. Use the controls and legends, then select a corridor or service. The third view tests terrain constraints without drawing a supposed railway alignment.

ARMENIA · SCHEMATICYerevanGyumriVanadzorAyrumHrazdanFioletovoDilijanIjevanShorzha / SotkYeraskhSyunik access objectiveNrnadzorAgarakAparan studyMylerAragats resortGyumri–Kars · official interfaceYeraskh–Nakhchivan · regional / conditionalNrnadzor–Agarak · TRIPP interface
Tourism demand point · not a station

01 · Infrastructure & engineering status

Open full map ↗

The schematic separates the core network, restoration, official interfaces, studies and the no-build comparator. Open the full relief map for detailed geography

Passenger services · illustrative
GEORGIA · internationalTÜRKİYEAZERBAIJAN / NAKHCHIVAN · conditional transitYerevanGyumriHrazdanSevanShorzhaYeraskhVanadzorAyrumTbilisi / BatumiFioletovoDilijanIjevanKarsNakhchivanSouth Armenia interface

Solid: existing / core patterns · dashed: conditional services · schematic, not a timetable. Drag to move; use + / − to zoom. Select a line for conditions.

02 · Passenger services · illustrative

Open full map ↗

One-seat service patterns, with conditional services clearly separated from existing / core services

03 · Topographic feasibility

Terrain before alignment

A terrain screening layer, not a railway alignment. Broad zones show where relief is likely to drive gradients, curves, tunnels, viaducts, winter operations and emergency-access requirements.

Aragats plateauBazum crossingVardenyatsVayk–JermukSisian–KajaranKajaran–MeghriMylerAragats resort study area
Moderate constraintHigh constraintVery high / tunnel-intensiveTourism demand points · not stations
Why endpoint height is not enough

Similar endpoint elevations do not make a corridor level. The railway must cross every ridge and valley between them; the controlling gradient and tunnel requirement are set by the intervening terrain.

Screening only · replace with official DEM, surveyed profiles, geology and seismic investigations before route selection

03 · Topographic feasibility

Relief-based screening of the crossings that need profiles, geology and tunnel evidence before any route can be selected

Every point is identified

Select a point to see its place name, station type, lines, status and programme phase

A blank area is not abandoned

Rail serves strong corridors; guaranteed buses and road investment complete lower-demand access

Lines are not surveyed routes

All new corridors require official GIS, alternatives, fieldwork, environmental review and design

Official project, conditional service

Gyumri–Akhurik design procurement has been announced. The domestic case still excludes assumed new border traffic and external funding

Programme reset

2027–2052 without automatic construction

Dates describe decision windows and deliverables. A study corridor does not become a built railway simply because the calendar reaches 2052.

2027–2031

Evidence first

Official GIS/DEM, asset and safety audit, demand model, preliminary profiles and engineering / hazard screening; Gate 0 and Gate S evidence
2030–2038

Fix the backbone

Justified R1–R4 renewal, stations and measured service improvements; R3 restoration only after engineering and demand validation
2030s–2040s

Open interfaces conditionally

Gyumri–Kars, Yeraskh–Nakhchivan and Nrnadzor–Agarak depend on design, agreements, border operations and funding; C1 needs revalidation
2040s–2052

Build only passed gates

Access studies may become rail, coach, feeder or road improvements, or be deferred; no fixed Kapan or Meghri railway completion year

Explore the project

A short home page,
detailed project sections

The project is organised by the decisions a government, funder, operator and community would actually need to make.

Live project

Gyumri–Kars

Reported design procurement, engineering interfaces and evidence required before international operation

Explore Gyumri–Kars
01

Network & regions

Relief map, R1–R4 and an access passport for every marz plus Yerevan

Open network
02

Service & demand

Timetable tests, fleet logic, demand cases, freight evidence, fares and energy

Open service plan
03

Options & costs

Four pricing buckets, revised scope, South Armenia Access Gate and fiscal tests

Compare options
04

Master plan & delivery

Integrated master plan, 2027–31 work, surveys, climate, safeguards and six gates

Open delivery plan
05

Evidence & full plan

Evidence labels, audit, priority sources and the complete 15-chapter report

Read full plan

The first deliverable

One integrated transport master plan

Before selecting a railway route, Armenia should compare rail, roads, buses, aviation, freight and no-build options through one demand model, one GIS, common standards and one fiscal envelope. The plan decides which problem each mode should solve and in what order.

See what the master plan contains →

Do next, not someday

The 2027–2031 decision window

2027

Programme authority, data room, asset and safety audit

2028

National demand model, official GIS and alternatives longlist

2029

Field surveys, reference case, consultation and Gate 0

2030

Funded reference designs, procurement and service specification

2031

Early renewal works, measured benefits and updated decisions